Children's Hospital Work Started
Akron Builders Bulletin
May 1926
Carmichael
Construction Co. Awarded Contract at Figure
of $428,598
Trustees of the
Children's Hospital awarded the contract
for the erection of the new hospital building at W. Buchtel and
Bowery to the Carmichael Construction Co., at
$428,598.
The excavating
work was started Friday, December 10th,
and it is their aim to have
the building completed November
1st, 1927.
The Carmichael
bid is for the building without refrigeration
plant, other equipment and
hospital details. The trustees hope to have the building
ready for occupancy January 1st, 1928.
"Children's Hospital Work Started." Akron
Builders Bulletin May 1926: 3.
Akron-Summit County Public Library
Children's
Hospital, "Y" Exchange Sites
Final
Legal Transfer To Allow Erection Of Two New Buildings is Made
Deeds in exchange, between the
Children's Hospital and Central Y.M.C.A. were given and recorded
Thursday.
In this, the final chapter of the
preliminaries for the erection of the new buildings for the
hospital and "Y" no money was paid by either side. The exchange
is even, the consideration in the deeds being the minimum, "one
dollar and other valuable considerations."
To Start Now,
Y.M.C.A.
In this transaction the hospital becomes owner of the plot of
ground at Bowery St. and W. Buchtel Avenue. Work of razing the
old dwellings to clear the site for the hospital has begun. The
Y.M.C.A. becomes owner of the old property of the Children's
Hospital at Buchtel and High Sts. where a new Central Y.M.C.A.
building will be erected as soon as the hospital vacates.
The present Y.M.C.A. building at State and Main Sts will be
sold.
"Children's Hospital, "Y" Exchange Sites." Akron Beacon Journal
26 August 1926: 19:5.
New Hospital Building
Akron Builders Bulletin
Nov 1926
Children's Hospital, corner Bowery Street and East
Buchtel Ave., John Andrews, chairman, Building Committee. Architects, Good
and Wagner, Mohawk Building. Fireproof construction, five stories, 100 bed
capacity, nurse home, laboratory, kitchen, laundry, etc. Estimated cost
$450,000. Bids close November 26, 1926, at 10 A. M., and will be publicly
opened.
"
New Hospital Building." Akron Builders
Bulletin Nov. 1926:14.
Akron-Summit County Public Library
Formally Exchange
Institution Sites
Children's Hospital And Y.M.C.A. makes Even Transfer Of
Properties
The Children's
hospital and the Y.M.C.A. have filed formal requests with the
common pleas court for permission to make an exchange of
building sites without any money changing hands. The trade was
agreed on by the respective institutions months ago and the
court application is nothing more than a formality.
The property
now owned by the Y.M.C.A. and which it had once been the
intention of that institution to build on is located at Bowery
and Buchtel. The new $450,000 Children's hospital is to be built
on this site. The property being traded by the Children's
Hospital to the Y.M.C.A. is at High St. and Buchtel Ave.
"Formally Exchange Institution Sites." Akron Beacon Journal
14 April 1926: 17:3.
|